Research Reactor Details - RA-6


Country Argentina (Argentine Republic)
Facility Name RA-6
Facility Number AR-0006
Status OPERATIONAL
Last Updated 2008/10/01


General Data
Owner  COMICION NACIONAL DE ENERGIA ATOMICA
Operator  CENTRO ATOMICO BARILOCHE
Licensing  CALIN-CNEA
Construction Date  1978/09/01
Criticality Date  1982/09/23
Safeguards  IAEA
Initial Cost
Total Staff 25
No of Operators 8


Technical Data
Reactor Type POOL
Thermal Power, Steady (kW) 500.00
Max Flux SS, Thermal (n/cm2-s) 1.1E13
Max Flux SS, Fast (n/cm2-s) 1.8E12
Thermal Power, Pulsed (MW) 0.00
Max Flux Pulsed, Thermal (n/cm2-s)
Max Flux Pulsed, Fast (n/cm2-s)
Moderator LIGHT WATER
Coolant LIGHT WATER
Natural Convection Cooling NO
Forced Cooling YES
Coolant Velocity in Core 4.07 M/S
Reflector GRAPHITE
Reflector Number of Sides 4
Control Rods Material AG,IN,CD,SS
Control Rods number 5


Experimental Facilities
Horizontal Channels 5
Horizontal Max Flux (n/cm2-s) 1.0E11
Horizontal Use STUDENTS EXPERIMENTS, BNCT
Vertical Channels
Vertical Max Flux (n/cm2-s)
Vertical Use Neutron Activation Analysis
Core Irradiation Facilities >20
Core Max Flux (n/cm2-s) 6.0E12
Reflector Irradiation Facilities 2
Loops Number
Loops Max Flux
Loops use


Fuel data
Origin of Fissile Material USA
Enrichment Supplier USA
Equilibrium Core Size 23
Plates per Element 19
Dimensions of Plates mtr
Rods per Element
Dimensions of Rods, mm
Tubes per Element
Dimensions of Tubes, mm
Cladding Material AL ALLOY
Cladding Thickness, mm 0.4
Fuel Material U3SI2ALX
Fuel Thickness, mm 0.52
Uranium Density, g/cm3 4.8
Burnup on Discharge, max %
Burnup Average, %
Last Shipment Year
Last Receipt Year
Fuel Fabricator CNEA, ARGENTINA


Utilization
Hours per Day  5
Days per Week  5
Weeks per Year  40
MW Days per Year  0
Materials/fuel test experiments  NO
Isotope Production  potential
  • Total Activity (GBq)
  •  N/A
    Neutron Scattering  NO
    Neutron Radiography  On-line beam hours: N/A
    Neutron capture therapy  Patients irradiated: N/A
    Activation Analysis  N/A
  • number of samples irradiated
  •  N/A
    Transmutation  NO  
    Geochronology  NO
    Teaching  Number of students: N/A
    Training  Number of operators/experimenters trained: N/A
    Other Uses  N/A


    Operating Experience
    Reactor Thermal Power Date of Operational for
    Category Type kW Criticality Construction Years Months
     RESEARCH  POOL  500.00  1982/09/23  1978/09/01  27  8