Research Reactor Details - SLOWPOKE-2, HALIFAX


Country Canada
Facility Name SLOWPOKE-2, HALIFAX
Facility Number CA-0010
Status OPERATIONAL
Last Updated 2009/06/23


General Data
Owner  DALHOUSIE UNIVERSITY
Operator  
Licensing  CANADIAN NUCLEAR SAFETY COMMISSION
Construction Date  1976/04/15
Criticality Date  1976/07/08
Safeguards  IAEA
Initial Cost 250 K C$
Annual Cost 120 K C$
Total Staff 2
No of Operators 2


Technical Data
Reactor Type SLOWPOKE-2
Thermal Power, Steady (kW) 20.00
Max Flux SS, Thermal (n/cm2-s) 1.0E12
Max Flux SS, Fast (n/cm2-s) 1.8E11
Thermal Power, Pulsed (MW) 0.00
Max Flux Pulsed, Thermal (n/cm2-s)
Max Flux Pulsed, Fast (n/cm2-s)
Moderator LIGHT WATER
Coolant LIGHT WATER
Natural Convection Cooling YES
Forced Cooling
Coolant Velocity in Core
Reflector BE
Reflector Number of Sides ANNULAR+TOP+BOTTOM
Control Rods Material CD
Control Rods number 1


Experimental Facilities
Horizontal Channels
Horizontal Max Flux (n/cm2-s)
Horizontal Use
Vertical Channels
Vertical Max Flux (n/cm2-s)
Vertical Use
Core Irradiation Facilities
Core Max Flux (n/cm2-s)
Reflector Irradiation Facilities 5
Loops Number
Loops Max Flux
Loops use


Fuel data
Origin of Fissile Material USA
Enrichment Supplier USA
Equilibrium Core Size 295
Plates per Element
Dimensions of Plates
Rods per Element 1
Dimensions of Rods, mm 4.73X220
Tubes per Element
Dimensions of Tubes, mm
Cladding Material AL ALLOY
Cladding Thickness, mm 0.51
Fuel Material
Fuel Thickness, mm 4.22 DIA
Uranium Density, g/cm3
Burnup on Discharge, max % 2
Burnup Average, % 1.5
Last Shipment Year
Last Receipt Year
Fuel Fabricator ELDORADO NUCLEAR, GE CANADA


Utilization
Hours per Day  4
Days per Week  1
Weeks per Year  52
MW Days per Year  0
Materials/fuel test experiments  NO
Isotope Production  NO
Neutron Scattering  NO
Neutron Radiography  NO
Neutron capture therapy  NO
Activation Analysis  N/A
  • number of samples irradiated
  •  N/A
    Transmutation  NO  
    Geochronology  NO
    Teaching  Number of students: N/A
    Training  Number of operators/experimenters trained: N/A
    Other Uses  NO


    Operating Experience
    Reactor Thermal Power Date of Operational for
    Category Type kW Criticality Construction Years Months
     RESEARCH  SLOWPOKE-2  20.00  1976/07/08  1976/04/15  34  7