Research Reactor Details - UWI CNS SLOWPOKE


Country Jamaica
Facility Name UWI CNS SLOWPOKE
Facility Number JM-0001
Status OPERATIONAL
Last Updated 2009/03/23


General Data
Owner  UNIVERSITY OF THE WEST INDIES
Operator  INTERNATIONAL CENTRE FOR ENVIRONMENTAL & NUCLEAR SCIENCES
Licensing  UNIVERSITY OF WEST INDIES
Construction Date  1982/01/01
Criticality Date  1984/03/13
Safeguards  IAEA
Initial Cost US $ 580 K
Annual Cost US $ 150 K
Total Staff 30
No of Operators 5


Technical Data
Reactor Type SLOWPOKE
Thermal Power, Steady (kW) 20.00
Max Flux SS, Thermal (n/cm2-s) 1.2E12
Max Flux SS, Fast (n/cm2-s) 1.0E11
Thermal Power, Pulsed (MW) 0.00
Max Flux Pulsed, Thermal (n/cm2-s)
Max Flux Pulsed, Fast (n/cm2-s)
Moderator LIGHT WATER
Coolant LIGHT WATER
Natural Convection Cooling YES
Forced Cooling NO
Coolant Velocity in Core
Reflector BE
Reflector Number of Sides ANNULAR+TOP+BOTTOM
Control Rods Material CD
Control Rods number 1


Experimental Facilities
Horizontal Channels
Horizontal Max Flux (n/cm2-s)
Horizontal Use
Vertical Channels
Vertical Max Flux (n/cm2-s)
Vertical Use
Core Irradiation Facilities
Core Max Flux (n/cm2-s) 2.0E12
Reflector Irradiation Facilities 4
Loops Number
Loops Max Flux
Loops use


Fuel data
Origin of Fissile Material USA
Enrichment Supplier USA
Equilibrium Core Size 296
Plates per Element
Dimensions of Plates
Rods per Element 1
Dimensions of Rods, mm 4.73X220
Tubes per Element
Dimensions of Tubes, mm
Cladding Material AL ALLOY
Cladding Thickness, mm 0.51
Fuel Material U-AL ALLOY
Fuel Thickness, mm 4.22
Uranium Density, g/cm3
Burnup on Discharge, max %
Burnup Average, %
Last Shipment Year
Last Receipt Year
Fuel Fabricator AECL, CA


Utilization
Hours per Day  5
Days per Week  5
Weeks per Year  45
MW Days per Year  4
Materials/fuel test experiments  NO
Isotope Production  NO
Neutron Scattering  NO
Neutron Radiography  NO
Neutron capture therapy  NO
Activation Analysis  INAA
  • number of samples irradiated
  •  1500
    Transmutation  NO  
    Geochronology  N/A
  • number of samples irradiated
  •  N/A
    Teaching  Number of students: 10
    Training  Number of operators/experimenters trained: 2
    Other Uses  NO


    Operating Experience
    Reactor Thermal Power Date of Operational for
    Category Type kW Criticality Construction Years Months
     RESEARCH  SLOWPOKE  20.00  1984/03/13  1982/01/01  25  2